A company sponsoring a photovoltaic project entrusted the installation of solar panels to a company insured by various insurers. After a fire in 2012 and subsequent malfunctions, it sued the insurers to obtain compensation for its damages.
The Court of Appeal rejected some of her claims, particularly against the main insurer of the panel manufacturer, ruling that the warranty exclusion clauses were valid and in accordance with the Dutch law applicable to the contract.
The Court of Cassation upheld this decision, considering that these clauses, although they limit the warranty to two years, are not contrary to French public policy. It also validates the stay of proceedings decided by the Court of Appeal on the precise amount of compensation, pending determination of the overall damage related to the serial defects. The Court concludes that this stay does not deprive the plaintiff company of its right of access to the judge. The appeal of the sponsoring company is rejected, and the decision of the Court of Appeal is upheld.
History
-
Hidden defects: confirmation of the suspension of the limitation period during the expert appraisal
Published on : 10/04/2025 10 April Apr 04 2025ActualitésSource: www.courdecassation.fr The purchasers sued the seller of an apartm...
-
Car wash and construction defect: ten-year warranty excluded for professional equipment
Published on : 03/04/2025 03 April Apr 04 2025ActualitésSource: www.courdecassation.fr A company operating a car wash entrusted a...
-
Photovoltaic panel fire: the Court of Cassation confirms warranty exclusions under Dutch law
Published on : 18/02/2025 18 February Feb 02 2025ActualitésA company sponsoring a photovoltaic project entrusted the installation of sol...
-
Contractual and tort liability: the limits of the project owner's direct action in tort in the face of contractual prescription?
Published on : 16/01/2025 16 January Jan 01 2025ActualitésPublicationsWhile the project owner can sue builders under contract and, in the alternati...
-
Defective photovoltaic panels: what are the limits for warranties for companies in liquidation?
Published on : 07/01/2025 07 January Jan 01 2025ActualitésPublicationsThe question of insurance cover raises complex issues, particularly in terms...
-
Sub-contracting in maritime transport: quasi-delictual action excluded
Published on : 03/01/2025 03 January Jan 01 2025ActualitésPublicationsIn the field of maritime transport, Article L. 5422-19 of the French Transpor...